Data center decommissioning: the process, the checklist and who does each part
Decommissioning is a move with no destination rack. Equipment still has to be inventoried, cleared of data, removed and accounted for, and the space handed back on time. Most of the risk sits in the handoffs between your team, the removal crew, the disposition firm and the landlord.
Checked November 2026
What data center decommissioning covers
A full decommissioning has four strands, and different firms usually own each one:
- The IT side: making sure every workload has moved and every backup is verified, so nothing still depends on the equipment being retired. Your team owns this.
- The data side: clearing or destroying every drive and device that holds data, with a record for each serial number. A disposition firm usually does this.
- The physical side: de-installing, packing and removing equipment, racks, cabling and debris. A removal crew does this, sometimes the same disposition firm.
- The contract side: disconnect orders, the date the space must be empty, its condition at handback and the final bill. You own this, with the landlord or provider.
Most published guides cover the first three and stop. The fourth is where the surprise invoices come from.
Data center decommissioning checklist, with an owner for every step
Each step names who does it and what you keep as proof. Keep the proof column: if an auditor or a regulator asks how a drive left your control, those documents are the answer.
| Step | Who does it | What you keep as proof |
|---|---|---|
| Inventory every device that holds data, by serial number | Your IT team | Signed inventory |
| Confirm nothing still runs on it: workloads moved, backups verified | Your IT team | Sign-off per system |
| Read the exit terms: removal deadline, restoration, abandonment | You, with the contract | Exit dates on the calendar |
| Order cross-connect and circuit disconnects | You, with the facility and carriers | Order numbers and end dates |
| Choose the disposition firm and the sanitization method | You, with the disposition firm | Written method and standard |
| Book dock time, badges and insurance certificates | The removal crew, with the facility | Confirmed dates |
| Sanitize or destroy media, on site or after transport | The disposition firm | Certificate listing every serial |
| De-install, pack and remove the gear | The removal crew | Custody record and a count against the inventory |
| Resale, recycling and settlement | The disposition firm | Settlement report with credit per item |
| Remove racks, cabling and debris; restore the space | The removal crew | Photos and the facility's walkthrough |
| Close the account and confirm the last bill | You, with the facility | Final invoice and written release |
Data destruction: NIST 800-88 methods and certificates
NIST SP 800-88, the US federal guideline for media sanitization, was revised in September 2025. Revision 2 moves away from tables of methods per type of drive toward a sanitization program, and it requires documentation such as certificates of sanitization. It sorts methods into three levels.
| Method | What it does | Usually used for |
|---|---|---|
| Clear | Overwrites the space a user can reach, usually in one pass, or a factory reset where overwriting isn't supported | Drives being reused inside your own company |
| Purge | Methods that defeat lab recovery; cryptographic erase is the main example, with conditions attached | Drives leaving your control for resale |
| Destroy | Physical destruction that leaves the media unusable. NIST now points to incineration or melting for high-sensitivity media and discourages shredding for medium and high categories | Failed drives and media too sensitive to resell |
NIST SP 800-88 Rev. 2, Guidelines for Media Sanitization (Sep 26, 2025), and its FAQ
The certificate is the part buyers most often accept too loosely. One certificate for “a pallet of drives” tells an auditor very little. Ask for one that lists each serial number, the method, the standard and the date, and match it against your inventory.
US law points the same way. The FTC's Disposal Rule requires businesses holding consumer report information to destroy or erase electronic media so the data can't practicably be read or reconstructed, and it gives checking a disposal company's independent audit as an example of due diligence. HHS says HIPAA covered entities need disposal policies for electronic health data and the hardware it sits on, and points to NIST 800-88.
Sources: NIST SP 800-88 Rev. 2 and FAQ (Sep 2025); eCFR, 16 CFR Part 682; HHS, HIPAA disposal FAQ.
What a weak handoff costs
The clearest public example of decommissioning gone wrong comes from a bank, and the failure was in the handoff. According to the SEC, Morgan Stanley Smith Barney hired a moving and storage company with no experience in data destruction to decommission thousands of hard drives and servers. The mover sold the devices on, some were resold through an internet auction site with customer data still on them, and the personal information of about 15 million customers was put at risk.
- The OCC fined two Morgan Stanley banks $60 million in 2020 over the oversight of the 2016 decommissioning of two data centers.
- The SEC fined Morgan Stanley Smith Barney $35 million in 2022.
- Six states settled for $6.5 million in 2023; New York's attorney general said the firm only learned of the problem when a buyer of an auctioned device found the data and contacted it.
The lesson for a buyer isn't that movers are dangerous. It is that the firm carrying drives out of the building has to be qualified for what happens to them next, and that you need a record for every device.
Sources: OCC News Release 2020-134 (Oct 8, 2020); SEC Press Release 2022-168 (Sep 20, 2022); New York Attorney General press release (Nov 16, 2023).
IT asset disposition and resale credit
IT asset disposition (ITAD) firms take retired equipment, clear or destroy the data, resell what has value and recycle the rest. For a decommission, their resale credit can offset part of the removal cost. A few things to settle with them:
- The commercial model. A buyback price up front, a share of resale proceeds, or a fee for recycling, item by item.
- Where sanitization happens. On site before anything leaves, or at their facility after transport under custody. On site costs more and removes a risk.
- The settlement report. Every serial number, what happened to it, and the credit or charge against it.
- Certifications. Who certifies them, and for what:
| Certification | Who runs it | What it tells you |
|---|---|---|
| R2v3 | SERI writes the standard; independent certification bodies audit facilities | Recycling and resale handled to a set standard, including data security from the moment a device arrives |
| e-Stewards | Basel Action Network, a nonprofit | Recycling standard that also requires NAID AAA certification |
| NAID AAA | i-SIGMA | Data destruction: process, facility security and staff background checks |
SERI, R2 page; e-Stewards, The e-Stewards Standard; US EPA, Certified Electronics Recyclers (updated Jul 31, 2026)
Handing back the space
The contract for the space you are leaving decides the deadline and the condition you leave it in. Published colocation terms give a sense of what to look for in yours.
| Term | What the published terms say | Source |
|---|---|---|
| Equipment left behind | Verizon colocation: may be treated as abandoned 30 days after the service ends. Switch: disposed of within 15 days of abandonment, and Switch takes no responsibility for data left on it | Verizon Business, Colocation Service guide; Switch, Customer Equipment Abandonment and Disposal Policy (Jan 2026) |
| Condition of the space | Verizon: returned in the condition it was delivered, wear and tear aside, with damage from removal repaired | Verizon Business, Colocation Service guide |
| Cross-connects | Equinix keeps billing a cross-connect until it is physically removed, which is no sooner than 30 days after you ask | Equinix Docs, Cross Connects FAQs |
| Storage at the dock | Equinix holds shipments at no charge for up to five days; Expedient holds them up to five business days, then returns or charges | Equinix Docs; Expedient policy (Aug 2025) |
Three dates to put on the calendar before you book a crew: the last day for disconnect orders, the day the space must be empty, and the walkthrough with the facility. Give the removal crew the restoration clause from your contract and ask for a scope that matches it line by line.
What decommissioning costs
There is no public price list for decommissioning either. The bill is built from removal labor (per rack, per device or per crew hour), packing and transport, data destruction priced per drive, recycling fees for gear with no resale value, and restoration work on the space, less any resale credit. The two numbers that move most are the drive count and the age of the equipment.
Put removal, destruction and resale on the same sheet so you can see the net figure. A cheap removal quote paired with a weak resale offer can cost more than the reverse.
Questions about data center decommissioning
What is data center decommissioning?
Shutting down a data center, a hall, a cage or a group of racks for good: confirming nothing still runs there, removing and disposing of the equipment, destroying or clearing the data on it, and returning the space under the terms of the lease or colocation contract.
How is data destroyed when a data center is decommissioned?
By one of three methods in NIST SP 800-88 Rev. 2: clear, purge or destroy, chosen by where the drive is going and how sensitive its data is. Whatever the method, you should get a certificate listing each drive's serial number, the method and the standard.
What certifications should a decommissioning company have?
For recycling and resale, R2 or e-Stewards, the two standards the EPA names for electronics recyclers. For data destruction, NAID AAA through i-SIGMA is the common one, and e-Stewards requires it. Ask for the certificates and check who issued them and the dates.
Can selling the old equipment pay for decommissioning?
Sometimes part of it. Newer servers, network gear and memory can have resale value, while old or failed equipment usually costs money to recycle. Ask for a settlement report that shows the credit item by item, and compare it with the removal price on the same sheet.
How long does decommissioning take?
The removal can take days. The schedule around it is set by the contract: the date the space must be empty, notice for disconnects, and how long the facility holds equipment before treating it as abandoned. One published colocation term allows 30 days after the service ends.
Can our moving company handle the disposal too?
Only if the disposal is done by a firm with data destruction credentials. Regulators fined one bank $101.5 million in total after a moving and storage company it hired, with no data destruction experience, resold drives that still held customer data.