Data center relocation services: what is included and how it is priced
A data center relocation is a short, expensive night at the end of weeks of paperwork. This page covers the work a relocation service should include, how the job gets priced, and the rules at each building that decide what is possible.
Checked November 2026
What data center relocation services include
Whoever you hire, a full relocation service covers the same run of work. A quote that skips one of these steps hasn't removed the work. It has left it to you.
- A survey of both buildings. Dock hours, freight elevator size and weight limit, floor loading, the path from the dock to your space, and the facility's vendor rules.
- Inventory and labels. Every device tagged with its origin rack and position and its destination rack and position, with serial numbers on file before move day.
- Cable and port records. Each cable labeled at both ends and the back of every rack photographed before anything is unplugged.
- De-install and packing. Gear out of the racks, into anti-static bags with foam ends, onto padded carts or into crates. Racks either empty or strapped to shock pallets.
- Transport. A closed, climate-controlled truck, ideally air-ride and dedicated to your load, with seals and a tracked route.
- Re-install and cabling. Racking to the destination layout and cabling to the labels, dressed to the new facility's rules.
- Power-on support. A crew on hand while your team brings systems up, after the equipment has had time to acclimate.
- Cleanup and retired gear. Packing debris out of the building, and anything not making the trip handed to a disposition firm.
What a data center relocation quote should list
These are the line items a complete quote carries for a move between two facilities. The quote builder narrows them to your job and fills in your quantities.
| Line item | What it covers | Usually priced |
|---|---|---|
| Site survey at both ends | Dock hours, elevator size, floor loading and the path from dock to cage set the crew, the trucks and the hours. A price made without walking both sites is a guess. | per job |
| Inventory and labels before move day | Every device gets a tag that ties it to its origin rack and its destination rack and position. That list is what you count against when the truck is unloaded. | per job |
| De-install and de-cable | Gear comes out of the racks, every cable end is labeled, and the back of each rack is photographed before anything comes apart. | per rack |
| Packing materials and crates | Anti-static bags, foam end caps, padded carts, and crates or shock pallets for anything heavy. Movers often charge packing per piece. | per piece |
| Racks shipped with gear mounted | Shipping a rack loaded saves the time spent unracking and reracking, but only a rack rated for shipping loaded can travel that way, strapped to a shock pallet. | per rack |
| Transport | Truck size, air-ride suspension, a closed and climate-controlled box, and whether the load goes direct or shares a truck with other freight. | per truck |
| Chain of custody and sealed loads | Numbered seals on the truck, a signed record at each handoff and a count against the inventory on arrival. Auditors ask for this when drives hold regulated data. | per load |
| Transit cover at the value of the gear | A carrier's default liability is set by weight or by its tariff, not by what the equipment is worth. Cover for the full value has to be arranged and written down. | per load |
| Insurance certificates for both buildings | Most data centers will not let a crew onto the dock until a certificate naming the building's owner is on file, sent days ahead. | per site |
| Re-rack and re-cable at the destination | Racking to the destination layout, cabling to the labels and dressing cables to the facility's rules. | per rack |
| Crew on site for power-on | People on site while your team powers up, to reseat a card or swap a part. Having the crew there is cheaper than calling it back. | per hour |
| Night and weekend labor | Night and weekend crews usually bill at a higher hourly rate, and some buildings only open the dock outside business hours. | per hour |
| No dock, stairs or a small elevator | No dock means a lift gate truck or hand carry. Stairs mean more people and more time per piece. | per job |
| Storage between pickup and delivery | If the destination is not ready, the gear waits in a secured, climate-controlled warehouse between legs. | per pallet per month |
| Packing debris removal | Crates, foam and cardboard leave with the crew, or the building charges you to haul them away. | per job |
| A named lead at each end | One person runs the schedule at both buildings and is the person you call when something slips. | per job |
Data center relocation cost
There is no current public price list for moving a data center. The figure most often repeated, an Info-Tech Research Group survey average of $120,000 per relocation, or about $10,000 per rack, sits on a page first published in 2010. It is a reminder of scale, not a quote.
Info-Tech Research Group, Data Center Relocation Budget Tool (page published 2010, updated 2019)
What you can control is whether every mover prices the same job. Quotes for this work come in different shapes: one mover prices per rack, another per truck, a third per crew hour, and each leaves out different lines. Put them on one sheet and the gaps show up.
| Cost line | How movers usually price it | What sets the amount |
|---|---|---|
| Labor | Crew hours or a price per rack, per device or per desk, with a separate rate for nights and weekends | Racks and loose devices, access at each end, the work window |
| Packing | Per piece, or as materials | How much leaves the racks, and whether racks ship loaded on shock pallets |
| Transport | Per truck, per day, or per mile on long hauls | Distance, a dedicated truck, air-ride, two drivers |
| Cargo cover | A declared value or a policy for the load | The value of what is on each truck |
| Destination work | Per rack for re-racking and cabling, per hour for power-on support | Whether you reuse cables, and how long the crew stays |
| Retired gear | Per piece or per drive, less any resale credit | How many drives, the destruction method, the age of the gear |
Lines that tend to go missing
- Night and weekend rates. If the window is a weekend, the quote should say which hours bill at which rate and what happens when the window runs long.
- Cover at the value of the load. A carrier's liability is often capped at a declared value or by weight. Ask for the limit per load in writing.
- Vendor support after the move. Some hardware support only resumes after the maker inspects gear moved by someone else, and that inspection is billed.
- Facility charges. After-hours dock time, freight elevator time and debris removed from a cage can be billed by the building, not the mover.
- Storage. Facilities hold deliveries for days, not weeks, so a gap between legs means a warehouse.
Facility rules that shape the move
Colocation facilities publish rules for vendors, and a crew that hasn't read them can lose the window at the dock. These come from the operators' own published rules.
| Rule | What the facility says | Source |
|---|---|---|
| Shipment booking | Equinix wants every inbound shipment scheduled at least 24 hours ahead; Verizon colocation wants five business days | Equinix Docs, Inbound Shipments; Verizon Business, Colocation Service guide |
| Access for the crew | CoreSite needs access authorized 48 hours ahead; QTS needs 48 hours for badges | CoreSite, Access Policies and Rules; QTS, Data Center Rules (Sep 2025) |
| Who unloads | Equinix staff don't load or unload vehicles, and Equinix says it is not liable for shipping damage | Equinix Docs, Inbound Shipments |
| Contractor insurance | QTS: $1 million per occurrence and $2 million aggregate general liability, $1 million auto, and a yearly certificate naming QTS as additional insured | QTS, Data Center Rules (Sep 2025) |
| Cardboard | Neither Equinix nor QTS allows cardboard on the data center floor; unpacking happens in receiving | Equinix Docs, Customer Installation Guidelines; QTS, Data Center Rules |
| Heavy cabinets | Expedient requires an engineering survey before shipping any cabinet over 1,500 lb | Expedient, Equipment Removal, Shipping, Receiving and Storage Policy (Aug 2025) |
| How long they hold it | Equinix stores inbound shipments at no charge for up to five days; QTS and Expedient expect removal within five days | Equinix Docs; QTS; Expedient |
Two of these change the plan more than people expect. Because cardboard isn't allowed on the floor, everything is unpacked in receiving and walked in on carts, which adds time per piece. And because deliveries are held for days, not weeks, a destination that isn't ready means paying for a warehouse between legs.
How long a data center relocation takes
The move itself is quick. What decides the date is everything that has to be in place first.
- Carrier circuits at the destination are usually the long pole, commonly two to four months from order. The cross-connect inside the building is fast by comparison: Equinix's provisioning target is 24 hours for up to three.
- Notice at each building. From 24 hours for an Equinix shipment to five business days at Verizon colocation, plus 48 hours for access lists at CoreSite and badges at QTS.
- Acclimation. Equipment that rode in a cold truck needs hours in its packaging before power-on. ASHRAE's table runs from 12 to 36 hours depending on how cold it got.
- Windows. A large room rarely moves in one night. Racks move in groups, one window per group, and each window needs its own crew booking and dock time.
Sources: Lightyear, What to expect during a DIA implementation (2025), for 60 to 120 days on new circuits; Equinix Docs, Cross Connects FAQs and Inbound Shipments; Verizon Business, Colocation Service guide; CoreSite, Access Policies and Rules; QTS, Data Center Rules; ASHRAE TC 9.9, Cold Weather Shipping Acclimation and Best Practices (2021).
Insurance and liability on a data center move
Three kinds of protection get mixed up in relocation quotes, and they pay out very differently.
| Protection | What it is | What to ask |
|---|---|---|
| Carrier liability | What the carrier owes by law for loss or damage. Under the Carmack Amendment, an interstate carrier may cap it at a value you declare in writing or agree to. | Ask what cap the bill of lading sets, and whether it is per pound, per piece or per load. |
| Declared value | A higher cap you buy from the carrier, usually at a higher rate. | Get the declared amount and its cost written into the quote. |
| Cargo or transit insurance | A policy that covers the goods themselves, bought by the mover or by you. | Ask for the policy limit per load and per day in storage, and who is named on it. |
Federal rules don't fill the gap for you. A for-hire general freight carrier must carry $750,000 of liability insurance for injury and property damage on the road, but its required cargo insurance is $0. A household goods mover must carry $5,000 of cargo cover, a fraction of one loaded rack. And if something is damaged, federal law gives you at least nine months to file a claim with an interstate carrier, so log damage at delivery and keep the photos.
FMCSA, Insurance Filing Requirements (updated Mar 26, 2026); 49 U.S.C. 14706 (Carmack Amendment)
Colo to colo moves
Moving between two colocation facilities doubles the paperwork: two sets of vendor rules, two certificates of insurance, two dock bookings and two access lists, on top of the contract at the place you are leaving. Three things to settle before you book a crew:
- The exit date at the old facility. Notice periods, the date the space must be empty, and what happens to equipment left behind.
- Cross-connect timing. New cross-connects at the destination before the first window, and removals at the origin ordered early, since some operators bill them for 30 days after you ask.
- The destination's move-in help. Some providers offer a partner or a credit toward the move. Ask, and put that partner on the same price sheet as everyone else.
Buyer questions
How much does a data center relocation cost?
There is no current public price list. The most quoted benchmark, an Info-Tech survey average of $120,000 per relocation or about $10,000 per rack, comes from a page first published in 2010. Price depends on the number of racks and loose devices, access at each building, the work window, the distance and the value of the load. The quote builder lists the lines a quote should price, so you can compare movers on the same terms.
How long does a data center relocation take?
The physical move is usually a night or a weekend per group of racks. The time before it is longer: the destination needs power, cabinets and live circuits, and new carrier circuits commonly take two to four months to deliver. Facilities also need advance notice for shipments and crew access, from a day to a week depending on the operator.
What information does a mover need to quote a data center move?
A count of racks and loose devices, the addresses and access at both ends (dock, freight elevator, stairs), the work window, the destination layout, whether racks ship loaded, the value of the equipment, and anything retiring rather than moving. The quote builder collects all of it and turns it into a price sheet.
Should racks ship loaded or empty?
Only ship a rack loaded if it is built for it: a shock pallet model, within the maker's shipping rating, which is far lower than its standing rating. One common 42U model is rated for 1,826 lb standing but 700 lb shipped. Otherwise the gear comes out and travels packed.
What insurance should a data center mover carry?
Enough cargo cover for the value of each load, in writing, plus the liability limits each facility requires of contractors. QTS, for example, asks for $1 million per occurrence and $2 million aggregate general liability. Federal rules require no cargo insurance at all from general freight carriers, so never assume it is there.
Is our data safe during the move?
It is as safe as the custody around it. Ask for numbered seals on the truck, a signed record at each handoff, a count against the inventory on arrival, and a truck that goes direct. Drives that hold regulated data can be encrypted or removed and carried separately.